Learnings
Outcomes
Due to the structure of the OpenLV trials, the outcomes are defined within discrete areas of
learning relating to the use of distributed intelligence platforms in a wide, business-as-usual
capacity across GB electricity networks.
2.1 Method 1 – Capacity uplift
2.1.1 Sharing the level of capacity uplift achieved through Method 1
Method 1 sought to test the hypothesis that having distributed intelligence available within
distribution substations would enable capacity uplift through automated analysis and
decision making based on observations of local conditions. Although the distributed
intelligence does not in itself create capacity uplift, it does instead enable opportunities for
capacity uplift.
Network Meshing
Method 1 also sought to demonstrate the ability of the OpenLV platform in instructing the
operation of physical devices through a network meshing trial. The network meshing trial
sought to allow two substations to run in parallel for a period of network requirement.
To implement network meshing, it should be noted that the OpenLV trial installed intelligent LV devices at the 11kV/LV substations as a means to form Normally Open Points (NOPs) that could be automated. This was an atypical approach as NOPs are typically found
midway between substation feeder cables in link boxes on public highways, rather than on the busbars at one of the substations in a pair.
The Method 1 network meshing trial demonstrated that it is practical to automate low
voltage switching devices through the use of the OpenLV distributed intelligence platform.
The sequence of calculation and switching detailed in SDRC 4 was found to operate as
expected, based on the control logic programmed into the system. The trigger thresholds
were adjusted through the period of active trials to allow for changing ambient temperatures
and network loading, whilst ensuring the system would continue to operate.
The network meshing trial also provided evidence that joining together LV substations as
demonstrated in the trial was unlikely to lead to significant capacity uplift between transformers. This is due to the load being transferred using the trial approach equating to
approximately half the load of one feeder. This is not sufficient to make a material change to
the proportional load experienced by a transformer; but it has already been acknowledged
that this was an artificial trial approach.
This trial also provided analytical evidence that points to a greater benefit of being able to
control NOPs located within link boxes, rather than having automated NOP on the LV bus
bars. By investigating the effect of meshing at the feeder link box level, it was shown that
there would be viable cases where meshing helped the feeder pairs share load much more
effectively, but this approach was unlikely to help create transformer uplift or materially
reduce losses. This is due to the load on either side of NOPs in the monitored networks being
closely matched – as such there is little realisable benefit from meshing networks in this
manner.
It should also be stressed, because of the maturity of automated link boxes at the time of
project initiation, that this trial did not demonstrate the effect of transferring customers
between substations by using a combination of automated link boxes and equivalent devices
to the ALVIN Reclose® units in one of the feeding substations.
Moving NOPs from the middle of feeders between to substations to on the busbars at
substation in a pair will always be effective in reallocating 50%-100% of a feeder’s load
between substations. Having a capability to move NOPs in this manner will also create
additional use cases not considered in this trial, an example being the capability to automate
LV customer restoration after unplanned outages.
Dynamic equipment ratings
DNOs allow a cyclic rating to be applied to their distribution transformers for limited
emergency conditions, during a period of additional back fed load for example, but only for a
time-limited period. These are based upon fixed and worst-case assumptions and typically
only allow a fixed uplift beyond the continuous nameplate rating.
Method 1 clearly demonstrated that having the ability to be able to apply real-time thermal
ratings, based on site-specific measurements of ambient temperature and loading could
create a dynamic rating beyond the transformer’s nameplate rating. This process was
continuous and undertaken locally, operating whilst power was available to energise the
OpenLV equipment. If deployed in a BAU scenario, the rating uplift would be available, in
effect on an ad-infinitum basis, rather than under emergency conditions.
For such dynamic ratings to be taken advantage of there would need to be the ability to plan
the network to remain within the expected dynamic ratings. Because the OpenLV trial
gathered site-specific ambient temperature, hot spot forecast and loading cycles, this
requirement would be satisfied.
This capacity uplift would be leveraged further when and if distributed intelligence devices
are able to instruct smart devices to respond to periods where the transformer was forecast
to exceed temperatures without additional intervention.
Such smart devices might include customer flexibility that was demonstrated through some
of the Method 3 trials or alternatively some form of network reconfiguration such as changing the network open points.
It is acknowledged that the network meshing trial was inconclusive. Smart link boxes were
not technologically available at the time of the project initiation but progress in this field is
ongoing.) A next development step may be to prove the concept of LV network load transfers
using smart link boxes. If smart link boxes can be proved effective, it provides another means
to create capacity uplift for the network.
Network meshing and Dynamic Thermal Ratings
To implement Dynamic Thermal Ratings and network meshing, the trial implemented three
different applications running of the OpenLV platform within the substations. These
applications were:
A load forecasting application.
A transformer Dynamic Thermal Ratings application.
The Loadsense application. This application reviewed data from the load forecasting
application and the Dynamic Thermal Rating application. When the forecast load
exceeded the forecast thermal rating, it would instruct the network to mesh.
Over the course of the active trials, across the five active pairs, network meshing was enacted
on 792 occasions. Each instance resulting in the automatic activation of network meshing
when determined to be beneficial to the network, and subsequently reactivation once the
network conditions allowed. On average, each ‘active network pair’ operated 160 times over
the 12-month period of active trials.
2.1.2 Establishing the level of capacity uplift that can be achieved in WPD’s
licence area and across GB
Method 1 has provided evidence in SDRC 4 regarding the amount of capacity uplift that could
be experienced across WPD’s licence areas and across the UK.
This analysis makes a conservative assumption that if dynamic transformer ratings were only
applied to transformers of a size 300kVA or greater (which is less than 27% of WPD’s total
population of LV transformers) then 6,350 MVA of total additional capacity would be created
across 39,500 WPD substations. Extrapolation of this analysis across the total LV substation
demographic of Great Britain would see a total uplift of 120,850 MVA in transformer
headroom.
It should be remembered that Open data platforms have multiple roles and capabilities and
as such, there are many other approaches to increase network capacity that can be enabled
by a Distributed Intelligence Platform that were not demonstrated within the OpenLV trials.
The same platform can provide functionality for multiple actors, such as the network
operators, businesses, academics, and community organisations, this is detailed below.
For example, if a community wished to have an OpenLV platform monitor their community,
then the incremental cost to deploy Dynamic Thermal Ratings would be minimal as it would
simply require the analysis package to be loaded onto the platform. Conversely, in cases
where an OpenLV data platform has been loaded into a substation to enable Dynamic
Thermal Ratings, then additional applications can be loaded on to create even more value.
Examples of these additional use cases may be pre-fault detection of LV faults or apps to track the amount of low carbon technology that has been installed in a LV network. For these
reasons, it would be misleading to decide that installation of the OpenLV platform should be
justified on solely based on the value created by Dynamic Thermal Ratings.
2.2 Method 2 – Community Engagement
The potential for widespread or targeted deployment of distributed intelligence benefits to
benefit communities was tested in the Method 2 – Community Engagement trials.
The OpenLV project found that communities, whether through established community
energy groups, housing associations or local community organisations, could leverage value
at a local level from the information provided by the OpenLV platform.
This was emphasised towards the end of the project trials when participating community
organisations requested continued access to the data for their community, requiring an
enduring solution to be installed in place of the trial equipment being removed.
2.3 Method 3 – Business and Academia
2.3.1 Did OpenLV demonstrate new ways to engage with business?
Even though commercial organisations were required to fund their own involvement in the
OpenLV trial, the available spaces for participation were oversubscribed.
The capability for the trial participants to access LV network data created new ways for DNOs and businesses to engage. The exact details of what the trial demonstrated can be found in SDRC 4.
There is a clear demonstration of the following use
cases:
A basis for customer decision making. We observed a number of organisations being
able to optimise control system settings and network capacity utilised on the basis of the load flow data that became available to them as a result of OpenLV. This is a new
proposition since DNOs have not traditionally been equipped to stream data to other
parties.
Basis for supply chain innovation. We observed some of the trial participants using project data to assess new value propositions or to refine existing products. In some cases, we also observed that the data enabled these parties to conduct testing on these product refinements. Without the development of this data, it would have been harder to obtain meaningful depictions of network behaviour.
New network management products. We observed several organisations creating platforms that enabled end-users or their equipment to respond to network loading information that is geographically specific in near real-time. Whilst it is acknowledged that the participants that demonstrated this did so on a limited basis, extrapolation of this capability would be a significant departure from the traditional business model that assumes customers are passive.
New forms of information visualisation. By making the LV network data available, other parties were able to disseminate this information to their stakeholders alongside other key indicators. One good example of this included electricity network data being presented alongside other information from across other energy vectors which gives the end-user an insight that cannot be obtained from data used in business as usual to date.
Lessons Learnt
Many lessons were learnt over the course of the OpenLV project. These lessons are collected
in this section of the close-down report, and the lessons learnt will be carried into future
innovation projects where relevant. To help the reader find lessons relevant to future
innovation projects, the lessons are grouped into categories, namely: hardware, software,
network, communities, businesses and academia, and other (project communication,
security, safety).
7.1 Hardware
It is better to over specify core components of the system for a solution such as OpenLV, for
example the ruggedised PC, thereby ensuring adequate processing power and storage for
project trials.
The hardware must fully support all software to be implemented in the project. Specifying
specific hardware components can be a useful means to minimise technical risks when
implementing software.
It can be useful to over specify sensors used in trials, to ensure the sensors are fit for purpose
for potential future applications which might require higher specified sensors than the
applications at time of deployment require.
The physical design of the system should consider the variety of physical spaces and
conditions that the system might be installed in. Different mounting systems allow for
hardware to be deployed in several different ways depending on which mounting system is
most appropriate on a site-by-site basis.
Well tested, off the shelf hardware reduces technical risk. For example, the LV monitoring
hardware used in the project had already been used by WPD in Business as Usual (BaU)
scenarios, as had the ALVIN® Reclose™ devices.
When equipment is installed on the LV network, all possible situations the systems may
instigate should be considered, together with the actions required to manage or mitigate
them. Training and documentation should be provided where actions are required outside of
normal operating practices. There should also be reminders on-site.
A dedicated test rig was extremely useful in the development of the OpenLV platforms. The
test rig should include all required sensors and be tested as early as possible to ensure
components can be tested for as large a time as possible before installation. A dedicated test rig allowed specific inputs into the system such that system outputs may be verified, in a way that would be technically extremely difficult to achieve in a live deployment. It is clear in this project, that a dedicated testing facility was a highly valuable asset and should be strongly considered for future network innovation projects.
Overall solution system requirements must be formally defined such that the FAT and SAT
documents cover testing all Project requirements.
7.1.1 Telecommunications
In project requiring adequate 3G/4G signal strength is required at deployment sites to ensure
reliable communications, outdoor antenna should be utilised if doubts exist over the signal
strength.
Communication monitoring should be performed with alarms set to report any issues. This
allowed hardware issues, commonly with routers, to be detected and rectified.
7.2 Software
Software requirements should be captured using well tested approaches. The MoSCoW
approach was the chosen approach for OpenLV.
Single end-user requirements may be delivered by more than one Application. The technical
requirements for these Applications must be cross-referenced to ensure compatibility.
The OpenLV solution focussed on building core functionality first, before adding additional
functionality later. This method proved effective as it allowed both earlier delivery of the core
functionality, and earlier testing, thus minimising technical risk to deployment.
The LV-CAP® operating system was based upon a Docker system architecture. This was
effective in allowing Apps (software) from multiple vendors to be packaged into separate
“containers”, designed to run on a shared operating system. The environment was designed
to allow a variety of programming languages to be used to create Apps, allowing fast
development of the overall platform.
Restrictions on technical specifications such as memory usage, processor usage and storage
space must be clearly communicated to developers as early as possible. Applications storage size was limited by reliability and cost of deployment to all required sites over the mobile
data network. It is clear from this that communicating technical specifications and limitations
in any network innovation trial involving software development should be done in detail and
at the earliest possible opportunity.
7.2.1 Platform Management
EA Technology performed the role of administrating the OpenLV platform for this trial. This
role included ensuring compliance of Method 3 apps against OpenLV protocols, in addition
to issuing security certificates to apps once they have passed the process. Certification here
refers to compliance of an app with the OpenLV protocol.
The project revealed that where relationships were strong between app developers and the
certification team, the certification process went smoothly because small problems were
found early and corrected. However, weaker relationships harbouring difference in
interpretation of the API rules, slowed down the certification process.
The skeleton app offered to software developers was successful in so far as developers who
made good use of the app progressed quickly towards development. Those who did not use
the app made progress towards certification more slowly. A common reason for developers
not making use of the skeleton app was an unfamiliarity with the programming language that
it was written in. Releasing skeleton apps in a wider variety of languages will help to overcome this problem.
It was concluded that greater familiarity with the API rules would have decreased the number
of failed certification attempts significantly. Developers attempting to use shortcuts in
automation led to serious failed certification attempts due to significant changes to the
source code being required before certification could be granted. In BaU context, these issues
would be overcome by encouraging greater familiarity with the API rules and creating a
culture of constructive feedback in the certification process.
7.2.2 App Development
EA Technology clarified the only requirement was a fully built app and a series of test inputs
to confirm its correct application. These tests were only to check correct integration of the
application into LV-CAP®, rather than to tests outputs from the application were correct or
to demonstrate the app met customer requirements. Access to the source code was not
required, avoiding conflicts of interest with potential app developers. Thirdly, the LV-CAP®
platform’s timestamping of data and data validity flags reduced the need for data cleansing
and thus time required significantly. OrxaGrid observed that the architecture of the OpenLV
platform enabled them to focus on app development, as valuable time was not taken up for
hardware installation of data network configuration and management. Valuable
opportunities for commercial development were identified as a result of new data sources
being available from the OpenLV platform, as well as greater potential deployment of existing
analytics packages.
Although LV-CAP® allows the use of a wide range of programming languages, it still imposes
restrictions on the memory usage, processor usage and storage space available to
applications. These restrictions must be clearly communicated to developers at an early
stage. The main limit on the storage size of applications is the reliability and cost of deploying them to all required sites over mobile data networks.
The LV-CAP® environment enables developers to write apps in any programming language.
This has enabled the overall platform to be built up quickly and easily utilising apps developed by multiple vendors using various programming languages (C++, Java and Go) and approaches to developing those apps.
Many applications were created to operate as standalone software containers, whereas
others required communication from other, paired containers to operate. There were also
multiple applications developed using IBM’s Node-Red development tool.
7.3 Network
The OpenLV trial demonstrated that decentralised analysis and control was able to present a
robust Method of automation for the Low Voltage network. Evidence for this came from low
voltage networks being reconfigured at times of simulated network stress. This was enabled
by OpenLV.
A Smart LV network device, located at one of a pair of substations, allowed the substations
to be meshed, enabling the substation to share load. This was an unusual approach, as in BaU LV networks are sectionalised by link boxes located between two substations. In the
arrangement utilised in this trial, temporary meshing of two transformers was shown not to
be an ineffective method of de-loading substation transformers. However, if cost effective
smart link boxes had been available at the onset of the trial, there was potential for significant
network uplift.
Method 1 investigated forecasting transformer capacity headroom available at LV
transformer, based on real-time measurements of transformer temperature and load
duration. This was successfully achieved, and the benefit estimated at a 6,350MVA capacity
uplift across 39,500 of WPD’s 140,000 substations. While it would have been possible to carry
out these calculations centrally, this would have relied upon reliable communications between the central location and the substations, which would be a costly operation, prone
to potentially harmful communication faults. This showed one of the high value propositions
enable be decentralised computing, further demonstrated by the results of these calculations
being shared with other apps serving the interests of Method 3 trial participants.
One of the main learning points from this stage of the project that seemingly separate
decisions combined to restrict the number of suitable substation pairs for use in the project.
A combination of decisions made during the initial project development stage together with
on-site restrictions limited the number of suitable sites. Each requirement or decisions
reduced the proportion of the network suitable for use in the trial. Despite these decisions
being made for sensible reasons, they still resulted in unintended consequences. Site
selections became a much more time-consuming process than expected for the eventual
outcome. The project trial’s system utilising LV-CAP® and ALVIN® Reclose™ devices was more difficult to implement than deployments of different hardware mixtures in the future.
7.4 Communities
As detailed in the section0 above, future projects should be cognisant of the level of technical
expertise within community groups and organisations such as parish councils.
During the project planning phase, it was assumed that a level of expertise would exist within
communities to enable development of applications, or to make sensible use of the data
available. In hindsight, it remained impractical for many communities, especially those
without specific domain knowledge, to make practical use of the available data. This was
despite the project planning on support for participating communities and designing the
interfaces from the distributed intelligence platform to be as simple to use as possible.
It should be remembered by future projects seeking to work with and utilise the local
expertise of community groups, that whilst they tend to be highly enthusiastic for anything
that would benefit their community, the challenge of their limited technical knowledge must
not be underestimated.
The OpenLV project has demonstrated that whilst community groups required assistance to
develop workable use cases for the project data, above and beyond that envisaged at the
start of the project, once data access was secured a wide range of effective projects were
implemented.
Community groups require different engagement approaches. Utilising tailored imagery and
communication styles ensured high levels of engagement by communities in the project.
Direct engagement with the community groups via telephone or in person contact was crucial
to ensuring continued engagement in the project. Having CSE and Regen, companies already
trusted by community groups, as part of the project team proved invaluable in successful
‘testing the market’ and recruitment stages for the OpenLV project. The length of the project
should be carefully considered, since the timeframes need to be long enough for
communities to see real benefits from their network.
The variety of App ideas from community groups was wider than expected. For example, 5
app idea under the banner of “policy, planning and retrofit programmes”, a topic not covered
in the suggested app ideas, were suggested. App ideas should be subject to clear assessment criteria to take into account any barriers, issues and risks (in this case set out in the Regen market potential assessment report).
The project showed that there was a strong desire from community groups about accessing
local network data to enable a greater understanding of the local electrical system, and
particularly the effect their actions had on the local network. High demand led to there being
more formal application to participate in the trail than the number of substation platforms
available in the trial. It is clear for future innovation projects that community groups have a
strong desire to understand the effect of their actions on their local electrical network.
To ensure a wide variety of engagement in the project, targeted marketing is required.