The project will demonstrate an alternative approach to identifying the location of transient LV (pecking) faults
while the cable is in normal service, before they have developed to a permanent fault requiring immediate
location and repair. The project will achieve this by installing 26 newly developed monitoring devices at
selected sites in the East Midlands region, and assessing the effectiveness of the associated distance to fault calculation results on real networks in normal service.
Benefits
The project aims to provide non-financial benefits to customers through a reduction in the number of supply
interruptions due to transient fuse-operating faults, reducing customer inconvenience. These same avoided
interruptions also have a potential financial benefit for WPD through a reduction in the number (and associated cost) of fuse operation incidents, and also through the regulatory Interruption Incentive Scheme
(IIS). These potential financial benefits are balanced against the cost of purchasing and installing such
monitoring systems. For a five year period, considering the East Midlands region, the potential savings of a
successful lower cost monitoring system are modelled as £686,000.
Learnings
Outcomes
Two detailed learning reports have been produced for the project, each detailing the learning from each of the two trials. Both can be found on the ALARM project page of the National Grid Electricity Distribution Innovation Website.
The project has also resulted in an additional innovation project Pre-fix to examine what is possible in terms of pre-fault detection for HV networks.
Lessons Learnt
The project successfully and accurately located a number of underground cable network faults and provided learnings about the real world performance of the DTF system on a live network with all of its quirks and features, and insight into how best to integrate information about potential issues on the network into the workflow of managers and field teams. The learnings below are summarised by category.
1.1. Event classifications and patterns
The sites chosen for the trial had a history of faults. Prior to installation of this equipment, local teams suspected that pecking events at these sites were relatively common but evidence for this was only anecdotal. As a result of this trial hard evidence has been produced about the frequency and behaviour of pecking faults. This evidence suggested that information taken from pecking events can be used as a leading indicator of power cuts.
1.2. Classification of transient events
The events recorded comprised (in approximate order of most to least common):
· Pecking events Phase to Neutral
· Pecking events Phase to Phase
· High inductive load start transients
· Fuse operation transients
· Fuse replacement transients
One of the key aims of the project was to automatically classify these transients to ensure only the pecking events were considered in the algorithm – e.g. to ensure load start transients were not misclassified as pecking events. The GridKey solution successfully isolated pecking events from other types of transients based on the specific characteristics of the transients and the majority of pecking events fitted the expected model and could be analysed.
1.2.1. Patterns of transient events
A number of distinct patterns of behaviour were observed across different installation sites:
· Regular pecking as single events, spaced by hours to days or even weeks
· Bursts of pecking events with e.g. 10 strikes in the space of a short period (seconds) separated by long periods of no events (days/weeks/months)
As expected there were also large variations between sites in both peak currents and overall duration of arcing leading to large variability in likely cable damage (and ozone gas generation – hence why using a “sniffer” or IR camera is not always successful in locating the fault).
Despite the sites having been selected as having a history of faults, some substations had no pecking events at all. However, at other substations there were hundreds of pecking events per month, albeit there was no evidence that all were eventually identified as faults.
Whilst there were occasions where fuse operations occurred without any or only a few previous pecking events, the trial proved that in the majority of instances pecking events did occur, and with sufficient frequency to build up statistics to locate the event on the network with a known prediction uncertainty in a reasonable timeframe. Where events happened more frequently, this allowed the location uncertainty to be lowered more quickly.
The trial showed a wide range of variability in correlation with prior pecking events, but where there were significant prior pecking events, there was a strong chance that the permanent fault developed at the location of the prior pecking events, as the pecking events were eliminated after the fault was repaired. However, there was not a strong indication of the timing of an impending fuse operation from the immediately preceding frequency of pecking events although physics would dictate that the more energy in the faults would tire the fuse more quickly and make it more susceptible to operating.
A learning was that some measure of the cumulative damage impact on the cable would be valuable in prioritising intervention or further investigation. This would be based on the frequency, current, and duration per event. Distinguishing between damage caused by lower current events at the far end of long feeders, high current events close to the transformer, and between short duration arcs and sustained multi-cycle arcing would be needed to evaluate the damage caused by pecking events.
1.3. Equipment performance
The GridKey equipment performed well in the field where the existing hardware was supplemented with an additional circuit board to allow the magnitude of the current spikes to be accurately measured. Two variants were trialled, differing primarily in their analogue resolution, and in their ability to manage multiple successive transients. It was found that the higher resolution captures did not materially improve location statistics, whilst reducing the time between captures did allow fewer transients to be missed during bursts of transients and hence quicker location statistics to be gathered but again this did not improve the overall location statistics.
1.4. Analysis of transient events to determine cause and location
Analysis and modelling learnings
Prior to this trial, it was expected that phase-phase arc transients would be common because the electric field levels are highest between adjacent phase conductors, but the trial showed that phase-neutral were far more common.
In addition, when there was a large pecking fault effecting a phase on one feeder, we observed large current transients on the same phase as the faulty feeder on other feeders connected to the same substation. These had not been expected prior to the trial of the equipment and we initially suspected instrumentation issues such as cross-talk within the electronic components. However, when the team considered the complete network model these were found to be explained by the model and once this was understood, these “parasitic” transients were eliminated from subsequent location analysis, eliminating some early misidentification of feeders with events. In fact, the presence of these transients further validated that the network model used by GridKey was correct.
1.4.1. Location statistics
The statistics (repeatability) of location for an individual pecking source varied significantly from one installation site to another. Some sites created relatively tight distributions, others relatively broad distributions. For those locations with broad distributions, a larger number of transients needed to be collected to achieve a reasonable degree of confidence in the actual location. A number of root causes of this variability were considered and eliminated:
· Equipment cross-talk
· Equipment resolution
· Level of load on the affected feeder
· Time of day
· Quality of fit for individual events
1.4.2. Dealing with multiple events at a location
In some instances where there appeared to be a broad distribution of predicted fault locations, we found that a single feeder could have more than one fault on it, but at different locations. In addition, these multiple faults could be on different feeders but also on the same feeder. These faults were initially displayed just as a single feeder but due to the multiple locations this gave a large position of uncertainty. As a result GridKey introduced a clustering algorithm to separate out events associated with different locations on the same feeder, and to analyse the statistics of these separately to give multiple sets of location information.
1.5. Validating the location information
A key part of this project was the validation of the locations identified using the GridKey system – this was done using different technologies or as a result of an actual repair.
There were 5 instances where fuse operations followed a number of pecking events on a feeder and multiple instances of the pecking events, and the local crews located and repaired the cable. Eliminating the cases where the transient event corresponding to the fuse operation itself was analysed, the agreement between the predicted and actual fault location was generally good and in general terms did reduce the time spent checking up and down the relevant feeder, the results being consistently within tens of metres.
1.6. TDR Verification Equipment
Validation with other industry tools was challenging and required experience to interpret and use. The Time Distance Reflectometry (TDR) systems when used correctly are able to provide extremely accurate fault location. Typically, each TDR unit only monitors a single three phase feeder whereas the GridKey system was monitoring up to 6 feeders simultaneously. There was also a marked contrast between the simplicity of a GridKey system providing a distance and associated uncertainty and the TDR system that required a degree of skill and understanding to both locate the installed equipment correctly and also to interpret the results.
However, there was generally good agreement obtained in those instances where the TDR equipment was successfully deployed.
1.6.1. Ozone detection
Using a CableSniffer to detect the ozone generated when there was a pre-fault pecking event was not successful. There were a number of reasons for this:
· Feedback from field crews was that even when there has been a fuse operation, the amount of ozone released is quite small
· Lack of a good process to get location information to field crews fast enough before the gases from the arcing had dissipated.
1.7. Making use of the location information
The true value of a fault location system is in connecting with maintenance and repair crews, either to enable proactive maintenance before a permanent fault occurs, or to speed the process of restoration after a fuse operation, embedding this process into Business as Usual (BAU).
1.7.1. Presentation of information
Engagement with the National Grid Electricity Distribution (NGED) team helped to change the representation of the statistics of fault location from a simple histogram based on frequency, to a smooth bell curve, to make the uncertainty of the distance calculations clearer. This bell curve presentation method also enabled potential multiple faults on the same feeder/phase to be shown more clearly.
The local teams use tablet computers to view their network maps. Ideally, there would be further development of the mapping system to enable the distance to fault system to highlight predicted fault locations directly on these maps, including where there are multiple possible locations because of branches or links, reducing the time to positively identify the locations of the potential sites to investigate.
1.7.2. Alerting the local field teams
A method of alerting local teams when a significant event occurs could be implemented to help in further identifying locations quickly using other techniques such as using a Sniffer, as there is a very small window of time after an arc when this is an effective method of fault detection This would enable higher probability of successful preventative maintenance prior to a permanent fault occurring. This would require BAU engagement to integrate with the existing work order management practices and systems that are in use.