LV Interconnected Pairs
- Status:
- Complete
- Project Reference Number:
- NIA_UKPN0074
- STRATEGY THEME:
-
- Optimised assets and practices
- START DATE:
- END DATE:
Project summary
- Funding mechanism:
-
- NIA_RIIO-1
- Technology:
-
- Active Network Management
- Asset Management
- Control Systems
- Fault Current
- Fault Level
- LV & 11kV Networks
- Expenditure:
- £661,000
Electricity networks contain equipment that operates at different voltage levels. Domestic customers are fed from the low voltage (LV) network. The LV network is fed from the high voltage (HV) network. The HV network is fed from the extra high voltage (EHV) network, and so on. When a fault occurs on the HV network, there is a cascading impact to the LV network that it feeds.
In more modern parts of the network, automation is used to prevent an LV outage when there is a HV fault. However, a large proportion of the LV network does not have any automation.
For the majority of LV networks, when a HV fault occurs, the LV network fed from the affected substation loses supply. This means that all customers fed from that substation experience a power cut.
Benefits
With the introduction of LV Interconnected Pairs, restoration times to those affected on the LV network will be reduced due to enhanced automation.
Gross financial benefit if all eligible substations received interconnected pairs technology: £1.75m per year
This is made up of CI and CML benefits.
.
[benefit per substation = HV fault rate x customers per substation x time that automation would save]
On average, we estimate that it takes 90 minutes to apply a backfeed.
The potential benefits across LPN, EPN and SPN are technically the same. The actual benefits will vary on a case by case basis based on network behaviour, such as where HV faults occur. This is analogous to the benefits from the Automated Power Restoration Software, which are reported each year in the E6 submission. See page 27 onwards in this document for more information on APRS: http://library.ukpowernetworks.co.uk/library/en/EnvReports201617/Environment%20and%20Innovation%202016-17%20Commentary_Final.pdf
Similar projects
Smart Network Design Methodologies.
Start date:
End date:
Status:
Technology:
- Active Network Management
- Asset Management
- Control Systems
- LV & 11kV Networks
Funding mechanism:
- Network Innovation Allowance
Alternative Jointing Techniques.
Start date:
End date:
Status:
Technology:
- Active Network Management
- Asset Management
- Carbon Emission Reduction Technologies
- Commercial
- Environmental
- Fault Current
- Fault Management
- Health and Safety
- LV & 11kV Networks
- Modelling
- Resilience
- Stakeholder Engagement
Funding mechanism:
- NIA_RIIO-1
Protection Solutions to perform for Lower Levels of Fault Current on AC Networks (PSL-FC).
Start date:
End date:
Status:
Technology:
- Control Systems
- Fault Current
- Fault Level
- Fault Management
- Network Monitoring
- Protection
- Resilience
- System Security
Funding mechanism:
- NIA_RIIO-2