This scope of this will include:
- Model refinement such as use-ability, dashboarding & data inputs
- Presentation of outputs (considering use of mapping tools to identify “hotspots”)
- Development of enhanced intervention methodology
- Establishment of “scheme allocation methodology” across all asset categories (just Primary Plant so far)
- Plant optimisation to achieve target levels of risk (with risk constraints)
- Plant optimisation to achieve unit cost reductions
- Alignment to the requirements of the Common Methodology
Development of the modelling capability around the high-volume low-value asset categories Based on our current understanding of NPg requirements decisionLab have developed this costed proposal for consideration.
Benefits
The project will be considered delivered once Northern Powergrid is in receipt of the final models with the agreed functionality.
(1) Tool Enhancement
- Optimise to achieve target levels of risk (with risk constraints) : Enhanced functionality over and above existing methodology successfully added to the existing model
- Develop NPg modelling capability around the high-volume low-value asset categories: HV cables, LV cables and pole mounted transformers added to the modelling environment
- Implement enhancements to functionality identified in Phases 1 to 4 during 2014/15: Enhanced functionality to existing methodology successfully added to the existing model
(2) Methodology Enhancement
- Evaluate and Improve underlying intervention methodologies: Internal workshops held to inform improved intervention modelling. Functionality added to models.
- Model synergies which can deliver efficiencies: Enhanced functionality over and above existing methodology successfully added to the existing model
(3) Investment Planning
- Optimise to achieve unit cost reductions: NPg able to carry out unit cost scenario analysis using the AIMMS model
- Incorporate an investment planning perspective: Enhanced functionality (over and above existing methodology) identified through targeted workshops and successfully added to the existing model
(4) Risk Outputs and Calculation
- To align to Common Methodology: Risk calculation methodology revised in accordance with the requirements of the Common Methodology
- Enhance model output functionality: The current sets of output pages would be fully reviewed with wider members of the NPg team.