IMGA221101
Start Date – 30/08/2022
End date – 11/11/2022
Cadent was completing medium-pressure gas mains replacement.
Due to the large-scale works of medium pressure, several collaborations have taken place in the phasing of the works.
• Strategic location for the City of Westminster.
• Covent garden underground station on the same road.
Collaboration with City of Westminster (Long Acre) – WC2E 9LH
- The City of Westminster was completing some drainage repairs outside 29 to 33.
- Cadent completing medium-pressure gas replacement works. Roughly 202m worth of replacement.
Collaboration with UKPN (Long Acre) – WC2E 9LH
- Cadent completing trail hole and CCTV 48IN cast iron main to inform for the LMPS program.
- UKPN completed the installation of a new electricity supply.
- Cadent utilized UKPN’s road closure.
Collaboration with Virgin Media & Thames Water & Camden (Theobald’s Road) – WC1X 8SP
- Cadent gas completed 48in cast iron gas main replacement.
- Virgin media – clearing out blockage in the carriageway.
- Thames Water constructed a chamber over the main and install gate valve.
Collaboration partners
Local Authority, Thames Water, UKPN, Virgin Media
Local authority
Westminster (Local Authority also a Collaboration Partner)
Length Of Collaboration (metres)
201-300
Level Of Collaboration
Level 2
Estimated Days Saved
57