Hydrogen is a key energy source for the Net Zero transition and is being considered as an alternative to natural gas. Over the next 5 years there is an ambitious work plan within the UK’s gas transmission and distribution industry to prove the viability of blending hydrogen into the UK’s existing gas networks.
This project seeks to develop a functional specification for the infrastructure required to blend hydroge from industrial clusters.
Separate projects will explore the adaptations necessary to commercial frameworks and in other blending scenarios
Benefits
Over a third of the UK’s carbon emissions are generated by the 83% of domestic homes currently using natural gas for heating and cooking. The UK is committed to reaching net zero emissions by 2050, so the gas we use needs to change. This project will support the transition towards net zero.
Learnings
Outcomes
Key Outcomes of the project
1. The Functional Specification
The Functional specification as drafted includes all known fundamental principles to provide a basis of design for future hydrogen blending-to-grid facilities. To summarise the document includes details of:
A. PRINCIPLES
1. FUNDAMENTAL PRINCIPLES
2. GAS QUALITY MEASUREMENT RISK ASSESSMENT
3. PROVISIONS OF THE HYDROGEN TRANSPORTER
4. PROVISIONS OF THE DELIVERY FACILITY OPERATOR
5. PROVISIONS OF THE GAS TRANSPORTER
B. CONTRACTUAL FRAMEWORK, ASSET OWNERSHIP AND OPERATING AND MAINTENANCE RESPONSIBILITY
6. CONTRACTUAL FRAMEWORK
7. ASSET OWNERSHIP MODELS
8. MINIMUM, MAXIMUM, & MIXED MODELS
C. FUNCTIONAL REQUIREMENTS
9. HYDROGEN PRESSURE REGULATION AND METERING
10. ACCURACY
11. HYDROGEN/GROSS CALORIFIC VALUE CONTROL
12. HYDROGEN SUPPLY
13. COMINGLED POINT
14. REMOTELY OPERATED VALVE
15. ODORANT INJECTION
16. FLOW WEIGHTED AAVERAGE CALORIFIC VALUE FUNCTIONALITY
17. GAS QUALITY AND SUPERVISORY SYSTEM
18. REMOTE MONITORING UNIT
D. DESIGN APPROVAL
E. TESTING
F. COMMISSIONING AND INITIAL VALIDATION
G. OPERATION
H. MAINTENANCE AND PERIODIC VALIDATION/CALIBRATION
2. Blending Technology Assessment
To support the development of the functional specification a technology assessment of blending equipment was undertaken to determine technology readiness levels available on the market, distances required to ensure a homogeneous blend could be achieved and indicative costs.
A number of solutions from different manufacturers were evaluated and CfD modelling was undertaken to determine the effectiveness of the blend to determine pipe distance requirements. The outcome of which, has indicated that homogeneous blending should be achievable within 10 pipe diameters of the mixing device, meaning that the blending facility can be quite compact and sited on the same skid if required.
3. Case Study Design
The case study design has indicated that a single injection skid unit could be produced to incorporate the requirements of the functional specification, minimising space, cost and complexity to install within the network. Note: single skid is not mandatory, but could prove efficient in some scenarios.
Lessons Learnt
Initial contracting was a challenge due to the RIIO 2 ‘GIGG’ collaboration agreement not being available at the time of project initiation. This took time to work through, delaying the start of the project. Lessons learned have been taken forward from this for other projects, and a new agreement has been developed and signed off by all networks for future use.
Final reporting also presented challenges due to facilitating the appropriate time for all networks to review and agree the final outputs. A satisfactory outcome was achieved, however took longer than expected. Stronger governance and structure is required where multiple contracting parties are involved in collaboration agreements going forward.